

Project Updates
February 2025
-
Maple Hill project – Project is complete and customers are being served.
-
Blackwater/Flower Gap project – DHCD recently awarded $480,000 toward this project. The engineer and LENOWISCO will continue to work on additional funding for the project. Notice has been received that ARC has awarded an additional $700,000.00 towards this project. The engineer has submitted a Coalfield Water Development application for funding in hopes that the remaining funds can be acquired for the project.
-
Cross Creek/Dryden/Hickory Flats Sewer project – At this time, DEQ has not funded the project but is willing to evaluate the existing offers to determine the best path forward on funding. Project is currently on hold until funding can be secured.
-
Western Lee Sewer project – Work between the PSA, the county, The Lane Group, LENOWISCO, the Army Corps of Engineers, and LMU is continuing on this project, with the main focus currently being easements.
-
Ocoonita-Smyth/Miller Chapel Interconnection – The project has been advertised with the Pre-Bid held on August 14 and the bid opening was held on August 28.
-
Middle Wallens Creek/Rasnic Hollow Extension – The engineer has submitted the project to the appropriate agencies for permits and is awaiting comments. Project should begin early spring of next year.
-
Phase III Hancock Co, TN/Lee Co, VA – The engineer received VDOT and continues to work on the stream permits and easements, which have proven tedious.
-
St. Charles Phase IV – Engineer has received VDH approval. Waiting on VDOT, Railroad, JPA, and E&S Permit. ​